In July, BCDC submitted a response to a two-part correction request received from EGLE and DNR for the permit application that includes Upper Crooked Lake floodwater pumping and Cloverdale Lake and Long Lake outlet improvements. On August 24th, EGLE sent correspondence to BCDC requesting additional information, primarily related to the Delton Marsh and impacts to … Continue reading WATSON AND CLOVERDALE DRAINS UPDATE
Month: August 2020
The project team submitted an EGLE permit for a temporary drawdown of Pine Lake on August 13, 2020.
Click this link to view more.